Ethiopian Energy Business Information
- September 2, 2018
- 0
[Spread eepBp if you like it]. Who are the principal government participants in the electricity sector? What roles do they perform in relation to renewable energy? ย Government
[Spread eepBp if you like it]. Who are the principal government participants in the electricity sector? What roles do they perform in relation to renewable energy? ย Government
Government policy in respect of the electricity sector is established by the Ministry of Water, Irrigation and Electricity. The electricity sector is regulated by the Ethiopian Energy Authority (EEA), which is an independent regulatory authority vested with the power to issue licences for the generation, transmission, and distribution of electricity within Ethiopia as well as the import and export of electricity into and out of the country. Ethiopian Electric Power (EEP) is responsible for the generation and transmission of electricity. The Ethiopian Electric Utility (EEU) purchases capacity and energy from EEP and distributes electricity to end users. Both EEP and EEU are public enterprises. They are wholly owned by the government of Ethiopia and governed by regulations issued by the Council of Ministers.
The majority of the energy generated by EEP is generated from hydroelectric resources. A relatively small percentage of power is generated from wind, geothermal and thermal sources.
ย
Although no independent power production (IPP) project has yet achieved financial close in Ethiopia, Ethiopia has recently determined that it should, as a matter of policy, use what limited financial resources it has available for the development of infrastructure to develop infrastructure in other sectors that are not as capable of generating self-sustaining revenues the electricity sector. As a result, Ethiopia has recently begun to examine legal and regulatory framework in Ethiopia in order to (i) determine whether it is capable of supporting an IPP programme, (ii) identify any changes that should be made to the legal and regulatory framework to facilitate the development of a successful IPP programme, and (iii) consider how best to approach the development of such a programme.
ย
The following is a list of the principal legislation governing the development of energy in Ethiopia:
Foreign banks can lend to an Ethiopian incorporated company only if they obtain an authorisation from the National Bank of Ethiopia, where the Ethiopian company cannot find adequate funding from Ethiopian banks. The authorisation by the company in Ethiopia to borrow money from abroad is granted by the National Bank of Ethiopia and is granted on a case-by-case basis.
ย
No.
ย
Foreign investors investing in an approved investment project may benefit from tax incentives depending on the type of investment they intend to make and the area in which the project will be located. An exemption from income taxation for a limited number of years is available to companies that are engaged in the generation of electricity in certain areas. Companies that invest in generation may also benefit from customs duty exemptions for capital goods and equipment. No incentives other than the foregoing are currently in place that would provide for additional incentives for investments in renewable energy projects.
ย
Ethiopia is a federation made up of nine ethnically based regions or states. The Constitution vests the right of ownership over rural and urban land, as well as of all natural resources, exclusively in the state and the nations, nationalities, and peoples of Ethiopia. The government of Ethiopia has wide-ranging powers deriving from the Ethiopian Constitution in relation to formulating and implementing major policy and institutional reforms aimed at creating an efficient and environmentally sustainable energy sector and at supporting investments in the electricity sector. Regions may enact laws in line with federal legislation and polices to implement the same, but in practice policy in the electricity sector is generally established at the national level.
ย
None have been established to date.
ย
In relation to the energy sector, two pieces of legislation are expected to pass in 2017. They are (i) the Draft Council of Ministers Regulation to provide for Energy Operations and (ii) a regulation to implement the Geothermal Resources Development Proclamation. The government is also developing a public-private partnership (PPP) proclamation. In line with Ethiopiaโs evolving policy to stimulate private investment in the electricity sector, it has become evident that the government will need to pass new laws in relation to IPPs and PPPs. The above legislation, if approved, will promote the participation of the private sector in building infrastructure and developing public sector projects.
The geothermal proclamation, which was promulgated in early 2017, aims to stimulate investment in geothermal resources. The development of geothermal resources is currently governed by generally applicable mining legislation, and its use to date has been limited as a result. The new proclamation will, if enacted, set forth the overall framework governing geothermal resources. The draft regulation will implement the proclamation at a more practical level by providing guidance on issues such as how licences should be applied for and issued to IPPs, and the requirements that projects must satisfy in order to qualify for a licence.
ย
As mentioned above, the major source of energy in the country is hydroelectric power. Although hydroelectric power has provided the majority of generation capacity for decades, there is a growing recognition that hydroelectric power alone will not be sufficient to serve the countryโs growing economy. As is also noted above, there is a growing recognition that private capital will be required in order to make the sizeable investments that will be required in the electricity sector over the near to medium term.
ย
Ethiopia is not a contracting party to either the New York Convention or the Washington Convention. Nonetheless, foreign arbitral awards are, as a general matter, enforceable under the Civil Procedure Code.
ย
As of mid-2017, EEP was conducting or planning to conduct two tenders for a total of 150 to 200MW of utility-scale PV solar projects. These would be the first PV solar projects to be procured by EEP.ย
ย
In our view, the principal issues are:
ย
EEP owns and operates several large hydropower projects. No hydropower IPPs have yet been developed.
ย
Not applicable.
ย
The use of solar panels in households and small businesses is becoming more widespread. The legal framework that would be necessary to support net metering is not in place.
ย
The only type of distributed generation we have seen so far (aside from backup diesel generation, which is relatively common in Ethiopia) involves the Ethiopian government entering into a PPA with an investor to provide energy for off-grid and mico-grid projects in rural areas.
ย
No framework for the promotion of micro-grids has been developed to date. Despite the lack of a framework, some communities have taken the initiative and invested in small micro-grids using a cooperative approach.
ย
Not applicable.
ย
None.
ย
Not applicable
ย
Investment by international investors in Ethiopia is strictly regulated. Investments by foreigner in transmission and distribution are prohibited. However, private developers are allowed to develop renewable energies in Ethiopia by obtaining a generating licence from EEA and entering into a PPA with EEP.
ย
As stated above, investments in Ethiopia by international investors are subject to strict regulation. However, where they are permitted to invest, investors may be permitted to import equipment (capital goods) needed for their projects free of any import duties. In general, where exemptions are not available tariff rates range from zero to 35 per cent.
ย
The EEA is the regulator of the electricity sector. Its powers derive principally from the Energy Proclamation. The EEA approves PPAs and has the power to grant generation licences. All foreign investments must first be approved by the Investment Commission or Ministry of Trade, as the case may be.
ย
Long-term PPAs entered into by EEP.
ย
No feed-in tariffs have been approved. EEP does not have an extensive track record from which these types of generalisations can be drawn.
Back to topย What government authorisations are required to operate a renewable energy project and sell electricity from renewable energy projects?ย
See question above.
ย
In practice, these obligations remain unsettled.
ย
Although no IPPs have achieved financial close to date, we would expect the principal sources of financing for first mover projects in Ethiopia to be loans from development finance institutions, multilateral development banks, and export credit agencies.
Foreign banks can lend to a company organised under the laws of Ethiopia only if they obtain an authorisation from the National Bank of Ethiopia, and only if the Ethiopian company cannot find adequate funding from Ethiopian banks. Authorisations to borrow funds from abroad are granted by the National Bank of Ethiopia and on a case-by-case basis.
ย
ย
ย ย ย ย Sources: gettingthedealthrough